Solutions

Periodic Façade Inspection (PFI)

Regulator-aligned inspection programmes delivered with engineering oversight and structured workflows.

NovaPeak inspector piloting a drone to scan a glass office tower façade

Full-Cycle Façade Inspection Delivery

NovaPeak supports full-cycle Periodic Façade Inspections in accordance with Singapore’s regulatory requirements, combining advanced drone technologies with certified facade inspection professionals.

Our structured approach ensures accurate defect identification, regulatory compliance, and actionable insights to help you maintain building safety and asset value.

Our Approach

100% Drone-Based Façade Scanning

High-resolution aerial data capture for complete façade coverage safely and efficiently.

10% Close-Range Tactile Inspection

Targeted verification by certified inspectors to validate and assess critical defects.

AI-Assisted Defect Detection & Classification

AI models identify and classify defects for greater consistency, accuracy, and speed.

Structured Reporting Workflows

Regulator-ready reports with photo evidence, mapping, and actionable recommendations.

Faster inspections. Reduced operational risk. Consistent and regulator-ready reporting across large building portfolios.

Designed for Facilities Management Companies, Professional Engineers, and asset owners managing multiple properties.

Solutions

Periodic Façade Inspection (PFI)Frequently Asked Questions

Key information for building owners and stakeholders about Singapore’s Periodic Façade Inspection requirements and process.

Inspection drone flying beside glass building façades

Overview & Regulatory Framework

1.What is Periodic Façade Inspection (PFI)?

PFI is a mandatory inspection regime in Singapore requiring building owners to assess and maintain the safety of building façades, implemented by the Building and Construction Authority (BCA) under the Building Control Act and Regulations.

2.Which buildings are required to undergo PFI?

PFI applies to buildings more than 20 years old or higher than 13 metres, including landed houses, temporary buildings, and buildings with a height ≤ 13 metres (Exemptions apply).

3.How often must PFI be carried out?

PFI must be conducted once every 7 years for applicable buildings.

Roles & Responsibilities

4.What are the key persons involved in a PFI?

A PFI involves the Competent Person (CP), Professional Engineer (Civil) or Registered Architect, Certified Façade Inspector (FI), Drone Service Provider (DSP), and Technical Managers (NovaPeak).

Inspection Process

5.What does a typical PFI involve?

PFI generally includes 100% visual inspection of all façade elements (via drone, camera, or direct observation), minimum 10% close-range inspection per elevation, defect detection, documentation and classification of findings.

6.What is a full façade investigation?

If widespread or serious defects are identified, the Competent Person (CP) may recommend a full façade investigation which may include close-range inspections, laboratory or on-site testing, and structural analysis where required.

7.What information is required before inspection?

Typically required: architectural & façade drawings, previous inspection reports (if available), repair & maintenance records, and access arrangements. A preliminary survey may be conducted.

Timeline & Planning

8.How long does a PFI typically take?

The duration depends on building size, height, façade accessibility, inspection method, weather conditions, and extent of defects. Early planning ensures smooth execution.

Post-Inspection & Compliance

9.What happens after the PFI report is submitted?

BCA reviews the report and may request clarification, joint inspections or presentations. Recommendations for rectification works must be carried out and certified by a Competent Person.

10.What are the responsibilities after inspection?

Building owners must carry out repairs promptly, maintain façade safety at all times, submit certifications where required, and report incidents (if any) within 24 hours.

11.Can PFI and PSI be carried out together?

Yes, both inspections can be conducted concurrently. However, they are different in scope and must be reported separately.

For further details or support with your PFI requirements, contact our team at NovaPeak.